PECO is in Town

PECO has begun a substantial improvement project in West Vincent Township. Here are the details…

Project Summary. Improvements will be made to existing electric infrastructure, so to help strengthen the network, improve reliability, and support growing energy needs.

Project Location. Work will occur at Birchrun Road, Davis Lane, Flowing Springs Road, Half Hill Road, Hollow Road, Jaine Lane, and Old Ridge Farm Road. Click here to view a map that shows these work locations.

Project Schedule. Tree trimming will take place in August. Infrastructure improvements will be installed throughout September, October, November, and December. All work is scheduled to be completed during daylight hours.

Project Contact. PECO will send contact information for the project liaison to the owners of properties along the affected roads. If you live in a work location that is shown on this map and you did not receive this information, please call West Vincent Township at (610) 458-1601.