10 Aug PECO is in Town
Three PECO improvement projects are now underway in West Vincent Township. Below find the details for each project…
PROJECT #1
Project Description. Improvements will be made to existing electric infrastructure, so to help strengthen the network, improve reliability, and support growing energy needs.
Project Location. Work will occur at Birchrun Road, Davis Lane, Flowing Springs Road, Half Hill Road, Hollow Road, Jaine Lane, and Old Ridge Farm Road. Click here to view a map that shows these work locations.
Project Schedule. Tree trimming has been completed. Infrastructure improvements will be installed throughout September, October, November, and December. All work is scheduled to be completed during daylight hours.
Project Contact. PECO will send contact information for the project liaison to the owners of properties along the affected roads. If your property is located in this area, and you did not receive this information, please call West Vincent Township at (610) 458-1601.
PROJECT #2
Project Description. Upgrading and installing new equipment, including new poles and tree-resistant aerial wires.
Project Location. Work will occur at Kimberton Road. Click here to view a map that shows the work location.
Project Schedule. The improvements will be installed in October. All work is is scheduled to be completed during daylight hours.
Project Contact. PECO will send contact information for the project liaison to the owners of properties along the affected roads. If your property is located in this area, and you did not receive this information, please call West Vincent Township at (610) 458-1601.
PROJECT #3
Project Description. Improvements will be made to existing electric infrastructure, so to help strengthen the network, improve reliability, and support growing energy needs.
Project Location. Work will occur at Davis Lane. Click here to view a map that shows the work location.
Project Schedule. Tree trimming has been completed. Infrastructure improvements will be installed throughout September, October, November, and December. All work is scheduled to be completed during daylight hours.
Project Contact. PECO will send contact information for the project liaison to the owners of properties along the affected road. If your property is located in this area, and you did not receive this information, please call West Vincent Township at (610) 458-1601.